PUBLIC NOTICE NOTICE OF DETOUR APPROVAL

Details

5/6/2026

Ad

Image for ad 3003001

Ad Text

PUBLIC NOTICE

NOTICE OF DETOUR APPROVAL
P. I. 0020260
CRISP COUNTY

Notice is hereby given that the Georgia Department of Transportation has approved the use of and the routing of a detour for this project.
The date of detour approval is: April 29, 2026
The proposed project is located along Booth Rd, approximately 5.3 miles Southwest of the unincorporated community of Wenona. This project proposes replacing the bridge over N Branch Swift Creek.
The proposed bridge will be two 10-foot lanes with 3.375-foot paved shoulders. The approach roadways would consist of two 10-foot travel lanes with 4-foot (2-foot paved) wide shoulders. The estimated construction time will be 18 months.
The proposed offsite detour will begin at the intersection of Antioch Rd. and Booth Rd. and follow Pateville Rd. to Booth Rd. The proposed detour length is approximately 2 miles. The normal travel distance along Booth Rd. is approximately 1.4 miles, resulting in a net detour increase of approximately 0.5 miles. The detour will be signed during construction.
Drawings or maps or plats of the proposed project, as approved, are on file and are available for public inspection at the Georgia Department of Transportation: For information or questions regarding the Detour Route, please contact:

Dennis Thacker
Area Manager
District 4, Area 5
dthacker@dot.ga.gov
2060 Newton Rd, Albany, GA 31701
(229) 430-4198

Cordele Dispatch:
May 6, 13, 20 and 27, 2026
PI 0020260